Construction Updates

Door and Hardware Replacement

An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

30%

Project Start:

4/20/2026

Project Completion:

Late 2026


Work is scheduled to resume in mid-October. All doors are expected to remain accessible throughout the project.

Restroom Remodel Project

An image of the Oakton College Leaf on a grey b

Restroom Remodel Project

Percent Complete:

 50%

Project Start:

Fall 2025

Project Completion:

Late 2026

Phase one of restroom renovations are complete and all restrooms at the Des Plaines and Skokie campuses are currently open.

Phase two restroom renovations, including rooms 2214 & 2216 at Des Plaines, are expected to begin in fall 2026.

Phase two restroom renovations, including rooms A149, A148, C236, C237 at Skokie, are expected to begin in fall 2026.

TenHoeve Refresh

Design phase of TenHoeve Center

TenHoeve Refresh

Percent Complete:

 1%

Project Start:

Summer 2027

Project Completion:

Late 2027

The project is in the design phase. The design team has been holding meetings with stakeholders for planning and design.

Des Plaine Campus Store, Welcome Center

An image of the Oakton College Leaf on a grey b

Campus Store, Welcome Center 

Stakeholders

Campus Store, Welcome Center 

Percent Complete

 5%

Project Start

Late Fall 2026

Project Completion

Early 2027

The installation of temporary construction walls and demolition will begin in mid-October.

The Des Plaines Campus Store has temporarily relocated to room 1275 (across the hall) during construction.