Construction

Appears to be an image of Oakly waving outside at Oakton College's Des Plaines campus.
The Division of Student Affairs has temporarily relocated to Room 2817.
The Division of Academic Affairs has temporarily relocated to Room 1420.
The Ten Hoeve Rooms at the Des Plaines campus are tentatively scheduled to be unavailable from Dec. 1, 2024 - Dec. 31, 2025.
An image of Oakton College's Des Plaines campus office rennovations.

Liberal Arts, Academic Affairs and Institutional Research Office Renovations (Des Plaines Floor 2)

Stakeholder(s):

Office of Academic Affairs, Office of Liberal Arts, Office of Institutional Research

Percent Complete:

97%

Project Start:

04/08/2024

Project Completion:

12/13/2024

Phase 1 has been completed. The Liberal Arts Department has moved into Suite 2180, and the Institutional Research has moved into Suite 2100. 

Phase 2 of construction for the Office of Academic Affairs is nearing completion. Furniture installation is in progress. Office of Academic Affairs will be moving into their newly renovated suite during the first week of December. 

An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

10%

Project Start:

TBD

Project Completion:

TBD

Kluber Architects is working on construction documents for phase 1, which entails repairs and replacement to exterior doors across both campuses. Construction dates will be established upon completion of construction documents and bidding process.

An image of the master construction plan at Oakton College.

Landscape Master Plan Project

Percent Complete:

93%

Project Start:

10/23/2023

Project Completion:

TBD

Sidewalk replacement at the Lee Building is ongoing and will continue into the week of Nov. 25.  

The landscape renovation work at ceramic’s lab patio is complete.

An image of the Oakton College Leaf on a grey background.

Baseball Field Renovation

Stakeholder(s):

Athletics Department

Percent Complete:

100%

Project Start:

Spring 2023

Project Completion:

Fall 2024

The Infield is 100% complete. Bullpens are 100% complete. The irrigation system is complete. Sod installation is complete. The scoreboard is installed. Punch List items are being completed. 

An image of the Oakton College Leaf on a grey b

Student Affairs, Information Technology and Access and Disability Resource Center (ADRC) Office Renovations (Des Plaines Floor 2)

Stakeholder(s):

Office of Student Affairs, Oakton IT, ADRC, Testing Center

Percent Complete:

4%

Project Start:

 

Project Completion:

 

Phase 1 projects for the IT Hub, Testing Center, and ADRC are out to bid. Phase 2 projects for the Office of Student Affairs, Workforce Development, and bookstore are in design.

Rendering of the new Oakton Library Learning Commons.

Des Plaines Library Learning Commons & Elevator Modification

Stakeholder(s):

Library, Learning Center, Center for Teaching Innovation, Math Labs (STEM), TRIO, IT Help Desk

Percent Complete:

 3%

Project Start:

 

Project Completion:

 

The architect is working on construction documents. The project is expected to go out for bid in December.